Influx observed while drilling out lower cement plug on well being abandoned |
||
IOGP Well Control Incident Lesson Sharing #23-3Plug and abandon operations were initiated on vertical well using a service rig. After the BOP was rigged up on the wellhead and pressure tested, the completion was pulled. A drilling assembly was then RIH to drill out an existing cement plug that was in place to isolate a lower zone. While drilling the lower abandonment cement plug, an influx was detected at surface. Once the influx was identified, the well was shut-in successfully on the BOP’s. This lesson sharing shows how important is to perform risk assessments of potential pressure sources from offset wells while performing infill well servicing / abandonment operations. See Figure #1 below for additional details. The Wells Expert Committee/Well Control Incident Subcommittee believes that this incident description contains sufficient lessons to be shared with the industry. We further encourage the recipients of this lesson sharing to share it further within their organization. Vertical gas producer with lateral offset production from deeper formation. Deeper formation was isolated on the incident well with a cement plug, shallower gas zone open above with perforations. Plug and abandon (P&A) operations initiated on the incident well: the completion was pulled from the well and a service rig was in the process of drilling out the cement plug (to fully isolate lower zone) when an influx was detected and the well shut-in. An attempt to kill the well via bullheading with overbalanced fluid was made but failed due to suspected underground flow from the deeper zone to the shallow (depleted) zone above. Offset steam-injection activities also identified as contributing to well kill complexity. Depressurization of lower zone from offset wells initiated, snubbing unit utilized to snub string above upper zone perforations and subsequently killed the well via bullheading. P&A completed post-depletion of lower zone. | ||
What Went Wrong?:
| ||
Corrective Actions and Recommendations:
| ||
Figure 1: P&A plan and sequence of events | ||
|
||
safety alert number: 349
|
||
Disclaimer
Whilst every effort has been made to ensure the accuracy of the information contained in this publication, neither the IOGP nor any of its members past present or future warrants its accuracy or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient's own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. The recipient is obliged to inform any subsequent recipient of such terms. |
||