IOGP Well Control Incident Lesson Sharing
<<< Back to Results

Printable version

Well flowed when BOP was removed to install the casing slips and pack off


In an unconventional field with known water flows due to injection zones, an intermediate hole section was drilled to TD and casing ran until stuck off bottom, all while managing water flow with mild H2S. The casing was cemented in place with no returns to surface, float was bumped and held differential pressure. At 50 psi compressive strength development after ~18 hrs post cement placement, intermittent water flow with shut in casing pressures necessitated higher compressive strength development wait time.

After WOC for 32 hrs to achieve 500 psi compressive strength with no flow observed, the BOP was lifted to install the emergency slips and pack-off. ~3 hours into this operation, flow was observed and the team reinstalled the BOP and secured the well with 57 psi shut in casing pressure and 60 bbls water influx gained. Pressure was bled off to zero and well was monitored for ~2hrs with no flow but observed to be on vacuum.

The annulus was filled with 15.5 ppg mud and decision was subsequently made to squeeze the annulus with 14.8 ppg cement slurry which was performed in three stages. After the squeeze job, the well was flow checked for 1hr with no flow. BOP was then nippled down, emergency slips and packoff were installed and tested to establish barriers to annulus flow.

What Went Wrong?:

  1. Offset operator was not cooperative to the request to shut in their 3 nearby injectors (800-1000 BPH waterflow intensity was experienced on this pad).
  2. Inability to land casing conventionally leading to use of emergency slips. (The C21 slip hanger with emergency seals and packoff were installed in +/-8hrs. The C22 version provides an automatic packoff seal, energized by casing weight enabling faster installation but is not available for the casing size ran. Both versions can be lowered through a full opening BOP stack into the wellhead with casing connection considerations).
  3. Cement contamination due to waterflow necessitating longer WOC time.

Corrective Actions and Recommendations:

  1. Well shall be completely shut in while WOC to reach required compressive strength.
  2. Continue to work with regulatory body (TRC) to make top job/cement squeeze a standard operating procedure option for when primary jobs experience severe losses.
  3. Work with business partner to reduce transition time for the cement during waterflow events.
  4. Reduce directional work in the bottom section of the hole section (more likely to land hanger in wellhead).


safety alert number: 339
IOGP Well Control Incident Lesson Sharing http://safetyzone.iogp.org/

Disclaimer

Whilst every effort has been made to ensure the accuracy of the information contained in this publication, neither the IOGP nor any of its members past present or future warrants its accuracy or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient's own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. The recipient is obliged to inform any subsequent recipient of such terms.
This document may provide guidance supplemental to the requirements of local legislation. Nothing herein, however, is intended to replace, amend, supersede or otherwise depart from such requirements. In the event of any conflict or contradiction between the provisions of this document and local legislation, applicable laws shall prevail.


IOGP