A well control incident took place while preparing to sever the drill string above the plugged BHA.
The well had experienced total losses, conventional LCM pills were unsuccessful, resulting in the decision to pump a “total loss” LCM pill. Pill was under displaced, and BHA was not stripped above pill for fear of damaging
the MPD annular. BHA became plugged.
While preparing to severe pipe, the well flowed and was shut in. Bullheading was attempted but failed as pressure was kept low for hole integrity concerns. Pipe was severed above BHA, but circulation was still not possible. Additional LCM pills were pumped,
followed by cement. Circulation regained. During Drillers Method circulation, high gas readings and oil contaminated mud seen and shakers. Circulation was stopped. No returns when attempting to restart circulation. Decision made to bullhead without concern
for open hole. Well killed and cement plugs pumped. Open hole abandoned.
IOGP Wells Expert Committee/Well Control Incident Subcommittee believes that this incident description contains sufficient lessons to be shared with the industry. We further encourage the recipients of this mail to share it further within their
organization.
Drilling 8 1/2" reservoir section using Managed Pressure Drilling, with hydrostatically underbalanced mud. Water zone with high pressure exposed in start of the section, oil reservoir with slightly lower pressure exposed further down. Two severe loss incidents
experienced while drilling, reducing the drilling window to 0.3 ppg.
Close to planned TD of the well, third severe loss zone encountered. LCM treatment unsuccessful. Decided to pump "total loss" LCM pill; underdisplaced pill and left BHA on bottom due to concerns with provoking a leak in MPD annular if stripping above the
pill. Attempted circulation and observed string plugged. Mobilized severing equipment, meanwhile decided to shut in well to stabilize losses and preserve mud; closing the BOP removed the MPD back pressure, reducing the bottom hole pressure. Loss rate decreasing
and levelling out while waiting for equipment.
While preparing to sever string above BHA, observed gain and shut in well again. Attempted cautious bullheading, limited by integrity of previous loss zone, unsuccessful. Severed string above BHA and attempted Driller's method, unable to establish returns.
Pumped LCM and cement and achieved formation integrity for circulating. 2nd attempt of Driller's method stopped due to early arrival of high gas readings at shakers, and heavily oil-contaminated mud. No returns when re-starting circulation. Decided to bullhead
well without constraints towards formation integrity, loss of section accepted. Placed cement plugs in open hole.
|