While drilling the 8 ½" section, an 8m3 drilling fluid transfer to the active pit was carried out from the reserve pit which was not equipped with sensors. At this point, a sudden increase of SPP and mud flow-out percentage were detected, and
bubbling was observed from the rig floor. The well was shut in, showing the following data: SICP stabilized at 2700 psi, SIDPP at 75 psi (float valve present in the BHA) and an approximated gain of 15 m3.
The well was controlled implementing the driller's method with a final MW of 2.24 (after four cycles of mud increments).
|
Disclaimer
Whilst every effort has been made to ensure the accuracy of the information contained in this publication, neither the IOGP nor any of its members past present or future warrants its accuracy or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient's own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. The recipient is obliged to inform any subsequent recipient of such terms.
This document may provide guidance supplemental to the requirements of local legislation. Nothing herein, however, is intended to replace, amend, supersede or otherwise depart from such requirements. In the event of any conflict or contradiction between the provisions of this document and local legislation, applicable laws shall prevail.
|