Safety Alert
<<< Back to Results

Printable version

Dropped V-door - high potential event

Country: USA - North America

Location: ONSHORE

Incident Date: 8 October 2022   Time: ---

Type of Activity: Drilling, workover, well services

Cause: Dropped objects

Function: Drilling


What happened?:

The rig contractor was rigging down from a well, and the logistics contractor was in the process of removing the V-door from the substructure. The lifting equipment was secured, with a tagline attached. Pins securing the V-door to the substructure were removed to allow lifting and removal of the V-door. As the load was being lifted, the crane reversed, and the load levelled. This created a bind in the load, causing one of the D-Rings to dislodge from the lifting hook. The V-door fell (approximately 3 metres) onto the drill line and managed pressure drilling line below.

All personnel were clear of the area at the time of the event, and no injuries were reported.

What Went Wrong?:

Inadequate supervision:

  • Supervisory personnel did not ensure crane inspection was conducted prior to the mechanical lift.
  • Supervisory personnel did not ensure rigging equipment was adequate for the task.
  • Onsite supervision failed to identify and properly manage onsite operational hazards and risks.

Violation of Procedures by Crew:

  • Onsite personnel did not follow proper lifting best practices.

Inadequate Hazard Identification:

  • Onsite personnel failed to identify and properly manage mechanical lifting risks.

Corrective Actions and Recommendations:

  1. Survey of Reiteration of Policy/Procedure Utilization: Management of the contractor reiterated to personnel the existing procedures for Crane lifting operations and confirm personnel understand how to apply these procedures.
  2. Equipment Replacement: Contractor personnel replaced the latch on the lifting hook and implemented additional (4 leg chain sling) to avoid improper lifting angles caused by load levelling.
  3. Post Incident Toolbox Talk and Sharing Lessons Learned: Shortly following the incident, onsite meeting was held with teams from both company and contractors. Event was discussed in detail to fully understand causes, inadequacies, and where utilization of procedures and safe work practices need to be applied to prevent reoccurrence. Expectation of following established mechanical lifting procedures was re-emphasized.
  4. Crane Inspection: Daily crane inspection conducted and documented prior to resuming operations.
  5. Retraining Recommendation: Company requested contractor to conduct refresher training to its personnel in identifying, assessing, and mitigating hazards/risks as they apply to specific operations.

Figure 1: Lifting hook(open safety latch)
figure 1

Figure 2: Improvised safety latch
figure 2


Safety Alert number: 354
IOGP Safety Alerts http://safetyzone.iogp.org/

Disclaimer

Whilst every effort has been made to ensure the accuracy of the information contained in this publication, neither the IOGP nor any of its members past present or future warrants its accuracy or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient's own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. The recipient is obliged to inform any subsequent recipient of such terms.
This document may provide guidance supplemental to the requirements of local legislation. Nothing herein, however, is intended to replace, amend, supersede or otherwise depart from such requirements. In the event of any conflict or contradiction between the provisions of this document and local legislation, applicable laws shall prevail.


IOGP